Procedure For Maharashtra Fire License | How To Apply For Fire License In Mumbai Maharashtra | Fire License Ke Liye Kaise Apply Karein

How To Apply For Fire License In Mumbai Maharashtra | Fire License Ke Liye Kaise Apply Karein  

Maharashtra Fire License
As stipulated by the Maharashtra Fire Prevention and Public Safety Act, 2006, possession of a fire license or clearance certificate is mandatory in order to obtain approval of the building plan from the Maharashtra Urban Development Authority. The Maharashtra Fire Service issues fire licenses to ensure compliance with fire protection requirements for premises. This article details the process of obtaining a Maharashtra fire licence.

Maharashtra Fire Safety and Life Safety Act
According to the Maharashtra Fire Protection and Life Safety Act, anyone who intends to construct a structure or building higher than 15 meters for a business or commercial project must apply for a Fire Protection Certificate from the Chief Fire Officer. Forms must be properly approved before being submitted with proper building plans to licensing authorities, which are local governments under state law.

Why Get a Fire NOC?

An individual must obtain a fire NOC or fire license under the following conditions:

A fire permit is required when seeking a business license or certificate of occupancy from a state civil board.

fire license is expected to conduct business and commercial activities as listed by the State Disaster and Fire Department.

A fire permit is required to demonstrate that the structure of the building is earthquake resistant or less likely to lead to fire.

Fire License Category

A fire license is required in Maharashtra to obtain the categories listed below.
  • Educational building.
  • Homes
  • Hotels
  • Hospitals and nursing homes
  • Nursing homes
  • Switchboards.
  • Assembly Building
  • Mixed-use Building
  • Commercial Building
  • Commercial Building
  • Industrial Building Low Risk
  • Industrial Building Medium Risk
  • Industrial Building High Risk
  • Warehouse Building High Risk
REQUIRED DOCUMENTS

The following documents are required to be submitted along with Maharashtra Fire License Application.
  • Proof of payment of fire protection fund fees and supplemental fire protection fees paid to MIDC.
  • Photo of the fire suppression system in working order.
  • Alarm or Ventilation Advisor Certificate.
  • Number of Proposed Towers (including Tower Numbers and Names)
  • Building Area Detail by Licensed Architect gives area per floor and details total covered area for each floor.
  • Preliminary Fire Approval Certificate of Conformance submitted by the company's designated licensing agency.
  • No fee statement from MIDC Accounts Department. (only if commissions are paid on incremental terms).

Online Application Procedure for No Objection Certificate / Fire License

Applicants can obtain a clearance certificate or fire license online by following the steps below.

Step 1: Applicants should visit the official website of Maharashtra Fire Department.

Step 2: Click Online Services on the home page of the portal.

Step 3: Select Provisional Approval and click Click here to apply for her E-Fire approval online.

Step 4: If you are registering for the first time, click New Registration on the next screen.

Step 5: The e-matriculation application form will open.

Step 6: Applicants must fill in the required information in the registration form and click the submit button.

Step 7: After registration, the current page redirects to the login page. Here, applicant 
must enter their login information, such as username and password, and click the Login button.

Step 8 : The Fire NOC application form will be displayed on the next screen.

Step 9: Applicants must provide information such as:

Building Name
NOC Type
Applicant's Email Address
Address Details
District Name
Mobile Phone Number
Building Type
Building Height
Land Area
After entering the data, upload the required documents.

Step 10: To complete the registration, the applicant must make an online payment after submission.

Step 11: After confirmation by the responsible authorities, the clearance certificate will be issued within the time limit.

AFFECTED AGENCIES  
The competent authorities responsible for issuing security clearances or fire permits are:

Division Firefighters - building area up to 10,000 m² and building height up to 24 m
Deputy Fire Chief Shi - Constructed-up area up to 15,000 square meters, building height up to 30 meters.

Chief Firefighter - Building area greater than 15,000m² meters and building heights over 30 meters.

Issuing Fire Licenses    

Once you have paid and submitted your application online, your application will be forwarded to your firefighter. The appropriate firefighter will assign the application to a committee of officers who will inspect the site/building and submit the report online within 7 days. The Commission then forwards the report to the appropriate firefighter, who either approves or denies the application. Applicants will receive an email containing the final approved certificate.

Documents required to obtain fire protection certification or preliminary certificate without objection

1. Applications should be addressed to the Director Maharashtra Fire and Emergency Services Mumbai.

2. An individual/company/corporation application on letterhead, duly stamped and signed by an authorized signatory or an architect/civil engineer appointed by the company, and accompanied by a company-issued letter of approval. You must also indicate the exact address of the site and the development control rules that apply to the proposed development. H. City Government, City Council, Local Fire Department.

3. 2 sets of all architectural drawings in metric system including block plan, typical floor plan, sections and elevations, etc. and a certificate of floor area calculation duly signed by the architect/civil engineer (basement, underground tank including no FSI areas such as ) ). , underground storage of solvents, etc.) If you have already received approval from the city planning authority, please attach the original set.

4. Brief information about the activities that take place in the building. If it is an industrial or storage building, you must provide a process flow diagram for the facility.

5. Brief description of fire protection and fire prevention measures For existing buildings, a complete set of drawings of the existing fire protection equipment must be submitted.

6. The building zoning plan should provide details such as the width of the main street where the property is located, adjacent property activity, width of the front door, other entrances to the property, basements if any, building details, etc. Activities performed in basements, surrounding areas, access roads around buildings and other details of industrial activities such as transformer yards, supply blocks, storage of raw materials and finished products, tank storage areas, storage of hazardous gases, liquids, etc. . LPG, 'A', 'B', 'C' grade petroleum products, LDO, etc.
7. For industries, the list of raw materials (including consumables such as LPG cylinders, storage of diesel generators, etc.) and finished products should be marked on the block diagram along with the quantities and storage locations within the plant.

8. Details of central air conditioning, fire dampers, ventilation systems, etc.

9. When handling, processing, or storing goods with government permission. Copy of permission from agency, government. Authorities such as the Explosives Control Officer (CCE), Excise and Excise. Gas Authority, MPCB, DISH, FDA, etc. A Civil Aviation Authority NOC is required if a high-rise building near the airport collapses.

10. If the building exists and has received an occupancy certificate, a copy of the fire permit and occupancy certificate issued by the relevant planning authority must be provided. An approved set of drawings must be submitted.

11. A copy of the company/company registration and license must be submitted.

12. The architect/civil engineer must certify that the plans for the proposed structure comply with the relevant competent authority's development control regulations and/or NBC-2005 regulations.

13. Receipt for fire protection fund fees. (This will be issued by the Director's office after initial submission of the file)

14. Receipt of fire protection fund fee. (This will be issued by the Director's office after initial submission of the file).

15. Provisional NOC is issued within 7 business days after receiving the UTR number for online payment.
Application for “ Final No Objection Certificate”

1. An application from an individual/corporation or a corporation-designated architect/civil engineer and a consent form issued by the corporation.

2. A set of all drawings approved by the city's local authority or the relevant planning agency, which is the special planning agency, and should include block diagrams, typical floor plans, sections and elevations, etc., and a preliminary NOC A copy should be included. , if any, issued by that office. Revised drawings of
or sets if changes were made during construction of the unit.

3. When changing the block plan of an industrial building of a company, the main entrance, the second entrance to the plot, the area surrounding the plot as in other companies, details such as streets, basements, surrounding areas, if any, factories Other details such as perimeter access roads, underground reservoir capacity, transformer yards, supply blocks, raw material and finished product storage areas, tank storage areas, and hazardous gas and liquid storage locations. LPG, 'A', 'B', 'C' grade petroleum products, LDO, etc.
4. If changes are made to the elevation and typical plan of the dwelling, details should include exits, emergency exits, travel routes along lines of movement, elevator and fire elevator provision, patio level water storage, fire pit locations. , fire extinguishers, hydrant systems, sprinkler systems, alarm systems, etc. Details of cellars, cellars, ventilation systems and exits.
Where changes are made to the elevation and typical floor plan of the dwelling, details include exits, emergency exits, travel paths along lines of movement, elevator and fire elevator provision, patio level water storage, fire pit locations , fire extinguishers, hydrant systems, sprinkler systems, alarm systems, etc. Details of cellars, cellars, ventilation systems and exits.

5. Every time the activity of industrial construction changes, the list of raw materials and finished products and their quantity and storage location in the plant should be marked on the block diagram. Detail of central air conditioning. Provision of fire dampers. building ventilation.

6. A certificate approved by the Maharashtra Fire and Emergency Services Directorate or Chief Fire Officer of the Local Government or Special Programs Department and issued by the Licensing Authority where a representative of the Fire Department conducts the final inspection of the premises. The inspection will confirm the recommendations made by the Interim NOC.
Awareness Programme

Fire Prevention & Protection
Malls
Schools
Industries
High Rise Residential
Do's and Don't's
Fireworks
LPG Cylinder
Earthquakes
Floods

Post a Comment

0 Comments